Stage 18&19 Titles Issued - May Newsletter
Stage 18 is completed with Titles issued 13 April 2023. Stage 19 has received S223/224C from Council and the titles were lodged to LINZ on 17 May 2023. Based on the current processing timeframes with LINZ, titles for Stage 19 are expected mid June 2023, with settlements being due late June 2023. The following documents are now available for both stages to assist with you Building Consent applications.Geotechnical Completion ReportServices As Built PlansDraft LT Plan...
May 1, 2023Stage 18&19 Completed - April Newsletter
Stage 18 is completed with Titles issued 13 April 2023. Stage 19 is now practically complete on site, and Works Clearance has been APPROVED by Council. The S223/S224C applications were lodged to Council on 27 April 2023 and will be issued by 12 June 2023. Based on the current processing timeframes from Council and LINZ, titles for Stage 19 are expected June 2023, with settlements being due late June 2023. The following documents are now available for both stage...
April 1, 2023Stage 18 Completed - March Newsletter
Stage 18 is complete and the s223 and s224C applications have been granted. Titles were applied for through LINZ on the 6th of March, and are expected to be released early April 2023. With titles imminent, now is a great time to consult with your solicitor to facilitate settlement(s). The following documents are now available to assist with you Building Consent applications.Geotechnical Completion ReportServices As Built PlansDraft LT PlanCouncil approved street numbersP...
March 1, 2023Stage 18 Nearly Complete - February Newsletter
Stage 18 is now practically complete on site with Works Clearance approved by Council. The s223 and s224C applications have been lodged and are expected to be approved this week, meaning we will be lodging for titles with LINZ in early March 2023. Stage 18 titles are therefore expected to be released early April 2023.The following documents are now available to assist with you Building Consent applications. Geotechnical Completion ReportServices As Built PlansDraft ...
February 1, 2023Welcome to Greenhill Park - January Newsletter
Welcome the first Greenhill Park Newsletter of 2023. We hope that you had a relaxing Christmas break with family and friends, and managed to find some nice weather along the way! The team here at Chedworth Properties is looking forward to a busy 2023 with the completion of Stages 18, 19 and 25A, construction starting on Stage 20, and plenty of other exciting projects in the pipeline for this year....