Stage 20 Progress - August Newsletter

Stage 20 – services completed and concrete works underway.

Stage 20 – services completed and concrete works underway.

Stage 20

Stage 20 continues to progress with drainage, services and basecourse all completed. The concrete works are well underway with around 75% of the footpaths and carparks now poured. Following the completion of concrete final work on the road will commence. 

At this stage the project is ahead of schedule, so looking very good for titles to be issued in May 2024 if not earlier.

Key Dates

  • Stage 18 Titles – ISSUED

  • Stage 19 Titles – ISSUED

  • Stage 25A Titles – WORKS CLEARANCE ISSUED - ON HOLD

  • Stage 20 – Tiles anticipated in May 2024.