Stage 20
Stage 20 continues to progress with drainage, services and basecourse all completed. The concrete works are well underway with around 75% of the footpaths and carparks now poured. Following the completion of concrete final work on the road will commence.
At this stage the project is ahead of schedule, so looking very good for titles to be issued in May 2024 if not earlier.
As Built Documents for Completed Stages
Key Dates
Stage 18 Titles – ISSUED
Stage 19 Titles – ISSUED
Stage 25A Titles – WORKS CLEARANCE ISSUED - ON HOLD
Stage 20 – Tiles anticipated in May 2024.
Contact Greenhill Park
For more information please visit our website https://www.greenhillpark.co.nz/, call Brendon on 0800 639 929, or email info@greenhillpark.co.nz.