      	      <item>
	         <title>Stages 22 &amp;amp; 23 Available - February Newsletter</title>
	         <link>http://www.greenhillpark.co.nz/blog/post/161543/stages-22-23-available-february-newsletter/</link>
	         	         <description>With the completion of Stage 24, Chedworth Properties is excited to release the next stages of Greenhill Park – Stages 22 and 23. Stage 22 has been released to our building partners, and the response has been great - 35 of the 41 sites now SOLD. We have 6 sites left, ranging from 285m2 to 433m2. We are about to start construction on Stage 22 in March 2026 and at this stage, are expecting titles by the end of 2026. Given the success of the Stage 22 release, we have also released Stage 23. Of th...</description>
	         <pubDate>Fri, 06 Mar 2026 15:17:01 +1300</pubDate>
	         <guid>http://www.greenhillpark.co.nz/blog/#post161543</guid>
	      </item>
      	      <item>
	         <title>Stage 24 Complete and Awaiting Titles - January Newsletter</title>
	         <link>http://www.greenhillpark.co.nz/blog/post/161495/stage-24-complete-and-awaiting-titles--january-newsletter/</link>
	         	         <description>Work on the Greenhill Park Neighbourhood Centre is progressing well, with all drainage now complete and contractors pouring footpaths and kerbs. We expect this stage to be completed in March 2026 and titles being issued mid 2026. Management is still working with potential tenants for all of the proposed buildings, and aiming to start work on the 1st stage of the centre (i.e. the supermarket) in 2026....</description>
	         <pubDate>Fri, 06 Mar 2026 14:14:57 +1300</pubDate>
	         <guid>http://www.greenhillpark.co.nz/blog/#post161495</guid>
	      </item>
      	      <item>
	         <title>Neighbourhood construction - November/December Newsletter</title>
	         <link>http://www.greenhillpark.co.nz/blog/post/161489/neighbourhood-construction--november-december-newsletter/</link>
	         	         <description>Chedworth Properties has commenced construction of the roading network and services that extend through the future town centre. Drainage works and roading undercut are well underway and this work will continue through this summer into early 2026....</description>
	         <pubDate>Fri, 06 Mar 2026 13:47:37 +1300</pubDate>
	         <guid>http://www.greenhillpark.co.nz/blog/#post161489</guid>
	      </item>
      	      <item>
	         <title>Stage 24 Asphalt Laid - October Newsletter</title>
	         <link>http://www.greenhillpark.co.nz/blog/post/155796/stage-24-asphalt-laid-october-newsletter/</link>
	         	         <description>Chedworth Properties has commenced construction of the roading network and services that extend through the future town centre. Drainage works and roading undercut are underway and this work will continue through this summer into early 2026....</description>
	         <pubDate>Thu, 06 Nov 2025 14:03:13 +1300</pubDate>
	         <guid>http://www.greenhillpark.co.nz/blog/#post155796</guid>
	      </item>
      	      <item>
	         <title>Stage 24 Roading Well Underway - September Newsletter</title>
	         <link>http://www.greenhillpark.co.nz/blog/post/153463/stage-24-roading-well-underway--september-newsletter/</link>
	         	         <description>The engineering approvals are being finalised with HCC currently, with sites works due to start once approved plans are received. We are also working with a number of potential tenants for the buildings and looking forward to announcing tenancies are those are formalized....</description>
	         <pubDate>Fri, 03 Oct 2025 15:22:06 +1300</pubDate>
	         <guid>http://www.greenhillpark.co.nz/blog/#post153463</guid>
	      </item>
      	      <item>
	         <title>Stage 24 Kerbs and Footpaths Progressing - August Newsletter</title>
	         <link>http://www.greenhillpark.co.nz/blog/post/152615/stage-24-kerbs-and-footpaths-progressing-august-newsletter/</link>
	         	         <description>The engineering team has submitted the detailed engineering drawings to HCC who are currently processing the Engineering Plan Approval, which has included detailed flood modelling. This will be worked through over with HCC and the team is working hard to gain approvals and start site works in the coming weeks....</description>
	         <pubDate>Tue, 23 Sep 2025 13:23:19 +1200</pubDate>
	         <guid>http://www.greenhillpark.co.nz/blog/#post152615</guid>
	      </item>
      	      <item>
	         <title>Stage 24 Services Install Underway - July Newsletter</title>
	         <link>http://www.greenhillpark.co.nz/blog/post/152614/stage-24-services-install-underway-july-newsletter/</link>
	         	         <description>The engineering team are currently working through the detailed design of the engineering plans for the Neighbourhood Centre, and management are continuing discussions with potential tenants. The site works are planned to commence in late August/early September, subject to HCC engineering approvals....</description>
	         <pubDate>Tue, 23 Sep 2025 13:20:06 +1200</pubDate>
	         <guid>http://www.greenhillpark.co.nz/blog/#post152614</guid>
	      </item>
      	      <item>
	         <title>Stage 24 Drainage Nearing Completion - June Newsletter</title>
	         <link>http://www.greenhillpark.co.nz/blog/post/152576/stage-24-drainage-nearing-completion-june-newsletter/</link>
	         	         <description>With the Resource Consent now issued CPL is finalising the builder for the 1st stage of the town centre, which will include the construction of the supermarket. Building Consent will be lodged in the following months following detailed design. In the meantime, the Engineering Approvals for the civil works have been lodged and are currently being processed by Council....</description>
	         <pubDate>Mon, 22 Sep 2025 16:24:02 +1200</pubDate>
	         <guid>http://www.greenhillpark.co.nz/blog/#post152576</guid>
	      </item>
      	      <item>
	         <title>Stage 24 Subdivision - May Newsletter</title>
	         <link>http://www.greenhillpark.co.nz/blog/post/146504/stage-24-subdivision-may-newsletter/</link>
	         	         <description>Stage 24 subdivision work is off to a great start with drainage&amp;nbsp;lines already being installed for the northern section of the&amp;nbsp;stage. The contractors are now working on the southern section&amp;nbsp;and work is progressing well.&amp;nbsp;At this stage we are expecting construction work for the&amp;nbsp;subdivision to be completed by the end of the year, however this&amp;nbsp;does depend on how much rain we get over winter! From there&amp;nbsp;titles will be applied for and we expect these between March&amp;nbs...</description>
	         <pubDate>Tue, 03 Jun 2025 12:03:00 +1200</pubDate>
	         <guid>http://www.greenhillpark.co.nz/blog/#post146504</guid>
	      </item>
      	      <item>
	         <title>Webb Drive Complete - April Newsletter</title>
	         <link>http://www.greenhillpark.co.nz/blog/post/145139/webb-drive-complete-april-newsletter/</link>
	         	         <description>Draft conditions have been received from Council. These are now being reviewed, and we expect the resource consent will be approved in the new few weeks. Engineering approvals are to be sought, and we are gearing up to start civil works in the next few months....</description>
	         <pubDate>Tue, 01 Apr 2025 00:00:00 +1300</pubDate>
	         <guid>http://www.greenhillpark.co.nz/blog/#post145139</guid>
	      </item>